Kings Cross London

We installed a 50mm track spacer followed by A252 reinforced mesh followed by concrete to a depth of 100mm,this total area was 430sqm we poured this area in 2this floor has had a light natural dry shake colour hardener from picsThe feature to this project is a 4.6 metre long bench which was casted ontop of finish floor aswell as 4 concrete stools which are stationed inside the changing rooms the architect specifically said these stools to be solid concrete so they don’t get moved/stolen. We returned to site once all works have finished to wash seal and buff the floor