Kings Cross – London
Case Study
Project specifications
We installed a 50mm track spacer followed by A252 reinforced mesh followed by concrete to a depth of 100mm, this total area was 430 sqm. We poured this floor area, which has had a light natural dry shake colour hardener. The feature of this project is a 4.6-metre-long bench. The bench was cast on top of the finished floor. In addition to this, there are 4 concrete stools, which are stationed inside the changing rooms. The architect specifically requested that these stools be solid concrete so they would not get moved/stolen. We returned to the site once all the work was finished to wash, seal and buff the floor.